Facility Expansion and Renovation

Although capital maintenance is performed annually, we believed that a renovation and small addition to our existing structure was necessary in order to meet increasing demand of our facility. In the fall of 2019 we opened our doors as a revitalized and expanded center. This page reflects the extent of the project, while also giving you a sense of the incredible center that will await you and your partners. Please visit our Virtual Tour to see an update of each completed space!

PROJECT BACKGROUND

The Seaside Civic and Convention Center (SCCC)  received approval from the Seaside City Council in August, 2016 to move forward with work to renovate and expand the current center. This followed years of research and development to study the most effective and efficient way to expand a center that had not received significant updating since the early 1990s.

In March of 2017, the SCCC hired Klosh Group, LLC to serve as the project manager for the now approved $15 million project. A short time later, the SCCC selected Portland-based Holst Architecture and Convergence Design of Kansas City for the contract to design a planned renovation and expansion of this 45-year-old facility. After a schematic design phase throughout the summer months, the following renderings and layout plans represent the most comprehensive design set to date.

In the fall of 2017, the Center added O’Brien and Company Construction to the project team. Holst, Convergence, O’Brien and staff continued to work hand-in-hand with final design elements throughout the winter months, and construction began on the nearly $15 million project in May of 2018. The project reached major completion in the fall of 2019

Follow our photo updates below!

June 4-10, 2018

June 11-17, 2018

June 18-24, 2018

June 25-July 1, 2018

July 2-8, 2018

July 9-15, 2018

July 16-22, 2018

July 23-29, 2018

July 30 – August 5, 2018

August 6-12, 2018

August 13-19, 2018

August 20-26, 2018

August 27 – September 2, 2018

September 3-9, 2018

September 10-16, 2018

September 17-23, 2018

September 24-30, 2018

October 1-7, 2018

October 8-14, 2018

October 15-21, 2018

October 22-28, 2018

October 29 – November 4, 2018

November 5-11, 2018

November 12-18, 2018

November 19-25, 2018

November 26 – December 3, 2018

December 3-9, 2018

December 10-16, 2018

December 17-23, 2018

December 24-31, 2018

December 31, 2018 – January 6, 2019

January 7-13, 2019

January 14-20, 2019

January 21-27, 2019

January 28 – February 3, 2019

February 4-10, 2019

February 11-17, 2019

February 18-24, 2019

February 25 – March 3, 2019

March 4-11, 2019

March 11-17, 2019

March 18-24, 2019

March 25-31, 2019

April 1-7, 2019

April 8-14, 2019

April 15-21, 2019

April 22-28, 2019

April 29 – May 5, 2019

May 6-12, 2019

May 13-19, 2019

May 20-26, 2019

May 27 – June 2, 2019

June 3-9, 2019

June 10-16, 2019

June 17-23, 2019

June 24-30, 2019

July 1-7, 2019

July 8-14, 2019

July 15-21, 2019

July 22-28, 2019

July 29-August 4, 2019

August 5-11, 2019 

August 12-18, 2019

August 19-25, 2019

August 26 – September 1, 2019

September 2-8, 2019

August 24-30, 2020     Storage/Bathroom Renovation

August 31-September 6, 2020     Storage/Bathroom Renovation

September 7-13, 2020     Storage/Bathroom Renovation

September 14-20, 2020     Storage/Bathroom Renovation

September 21-27, 2020     Storage/Bathroom Renovation